Sewer built using a double-containment pipe system

The Great Brombachsee is located around 40 km south of Nuremberg. The lake was opened in 2000 and is home to one of Germany’s largest dams, both in terms of surface area and storage volume. In response to the growing number of tourists, 20 floating houses were built on the lakeshore in February 2018. In addition to various other amenities, each house has a carefully coordinated sanitation system. The sewer pipes were welded using the double-containment AGRU Poly-Flo pipe system, made from PE 100-RC.
Wastewater is safely conveyed through a pressurised wastewater pipeline in the Brombachsee to a collection tank on the mainland. From there, the collected wastewater is sent on to the wastewater treatment plant. Special precautions must be taken when constructing and operating sewers in water catchment areas such as the Brombachsee. In this zone, high-risk pressurised pipelines must have double containment. Another challenge in planning and carrying out the project was the varying water levels. The pipes connected to the pontoons, which serve as floating foundations for the houses, extend to the mainland. For this reason, the pipeline had to be flexible enough to accommodate differences in water level of up to 8 m.
A 10 m-wide section of the shoreline had to be crossed using horizontal directional drilling.
Troubleshooting
FRANK GmbH succeeded in providing an economical and technically sound solution to all these challenges with the AGRU double-containment “Poly-Flo” pipe system, made from the thermoplastic material PE 100-RC. The Poly-Flo pipe system features a double-wall pipe extruded as a single strand, offering a high level of system security. Potential leaks in the inner pipe can be detected in the annulus by the leak detection system installed there. The outer pipe prevents the conveyed medium from entering the lake. A positive-pressure leak detection system was selected to monitor the double-containment pipe system. The positive-pressure method monitors both walls of the double-wall system for leaks. The operating monitoring pressure is higher than any other internal or external pressure on the walls, so a drop in pressure indicates a leak.
A constant monitoring pressure of 1.5 bar is maintained in the annulus of the Poly-Flo pipe system. The pipes and fittings of this highly compact double-containment pipe system are produced in a single manufacturing process, by extrusion for the pipes and moulding for the fittings. Continuously extruded webs make it easy to align the inner and outer pipes. One advantage of the continuously extruded webs is that the pipes can be separated at any point when required for isometric layout. Thanks to the considerably smaller component dimensions, installation is straightforward, even in confined spaces. The individual double-containment pipe components were joined by simultaneous welding. As this process welds the inner and outer pipes at the same time in a single step, it was the optimal solution from both an economic and a processing standpoint. A double-containment pipe made from PE 100-RC is highly flexible, enabling it to accommodate the considerable height difference between the transition point on the mainland and the pontoons without additional fittings.
AGRU Kunststofftechnik extrudes the Poly-Flo double-containment wastewater pressure pipeline as a single strand.
Why PE 100-RC?
PE 100-RC was selected for the material. The innovative PE 100-RC material, which is resistant to cracking, offers much greater resistance to slow crack growth than PE 100. Thanks to this increased resistance to stress cracking, pipe systems made from PE 100-RC can also be installed without a sand bed. In addition to its resistance to corrosion from the surrounding lake water, PE 100-RC’s ability to withstand temperature fluctuations in the Brombachsee was an advantage over other materials. As the wastewater may also contain larger quantities of solids, PE 100-RC’s excellent abrasion resistance was another decisive factor in the material selection.

The highest safety requirements apply to wastewater disposal in a water catchment area. AGRU’s Poly-Flo pipeline is equipped with a leak detection system in the annulus.
Implementation
The pipes serving as connecting sewers between the individual houses are made from Poly-Flo PE 100-RC OD 90/63 pipes manufactured by AGRU Kunststofftechnik. After installation, the wastewater collected from all the floating houses is pumped to the main pipeline. The main pipeline, made from Poly-Flo PE 100-RC 160/110 pipe, and the connecting pipes were welded directly on site. As there is a 10 m-wide public footpath between the lake and the wastewater tank on the mainland, it was necessary to bore beneath it. The so-called horizontal directional drilling method (HDD method) was used. The pipe section had to be made heavier so that it could slowly sink to the bottom of the lake. This was achieved by filling the pipe with water and adding pipe clamps embedded in reinforced concrete. The project was completed within the planned timeframe. The “Floating Houses” became very popular shortly after completion and offer tourists comfortable accommodation on the beautiful Brombachsee.