General

Water main rehabilitated without excavation

Water main rehabilitated without excavation

In Bad Hall, one of the oldest drinking water mains still in service needs to be replaced. The old DN 250 fibre-cement pipe has long since reached its capacity limit. In addition, several pipe bursts have had to be repaired over the years. AGRU protective casing pipes, DN 315 and SDR 17, installed using the pipe bursting method, are now being used as replacements. This ground-friendly rehabilitation method avoids having to remove the old pipeline and ensures that the new pipeline follows the original route exactly.

A 450 m-long DN 280 pressure main to the Voglhub elevated tank and a 1,800 m-long DN 315 transmission main, with a branch from this elevated tank, will be installed. On the way to the Pfaffenwimm elevated tank, the transmission main overcomes a height difference of 17 metres, and pressure in the pipeline system reaches 5.5 bar at its lowest point.

The last fibre-cement pipe was installed in 1979

“Unfortunately, there have been a few pipe bursts in this area in recent years,” says Anton Pöllabauer, managing director of the Bad Hall Kurbezirk Waterverband. As the operator of the new PE pipeline system, quality and service life are very important to him: “The last fibre-cement pipe was installed in 1979. However, for more than 20 years we have installed only AGRU PE pipe systems. We have rehabilitated older water mains using AGRU protective casing pipes and pipe bursting and ploughing methods, and have had very good results. We expect the newly installed pipes to have a service life of at least 50 years.”

In the reception pit, sections of the pulling rod are removed from the machine and stacked

Lower installation costs thanks to long pipe strings

To ensure the most economical installation possible, the pipe bursting method is being used again. The principle is that installation costs decrease as the length of the pipeline strings being pulled in increases. The contractor, WDS Bau GmbH, an Upper Austrian civil engineering specialist known for its careful pipeline installation, calculates the maximum insertion lengths between the launch and reception pits based on ground conditions and the resulting pulling forces, which can reach pressures of up to 250 bar. Pipe strings up to 144 m long are made on site by butt-fusing 18 m-long protective casing pipes supplied by AGRU Kunststofftechnik GmbH. Sureline III pipes with a protective casing provide double security, as the stress-crack-resistant PE 100-RC core pipe is protected from fragments of the burst pipe by a scratch-resistant PP casing as the pipe is pulled into place. Another advantage is the fast butt fusion made possible by factory-stripped pipe ends. AGRU Kunststofftechnik supplied a CNC-controlled butt-fusion machine for the welding process. Thanks to the new technology, temperature, pressure and time are pre-programmed, ensuring the quality of the welds. The parameters for each individual weld and the welder’s name are also documented. The completed pipe strings are then pulled into the old pipe using a crack-resistant lining. Pipe bursting is a cost-effective method for rehabilitating pipelines made of brittle materials without excavation. Breaking up the old pipe makes it possible to pull in a new pipe with a significantly larger diameter. Some preparatory work is required.

The bursting head and expansion cone are already mounted on the pipe

Pipe bursting: how it works

First, a camera is used to inspect the old pipeline. Metal or cast-concrete fittings cannot be broken up and must therefore be removed using open-cut methods. The launch and reception pits are then excavated at precisely specified intervals. The bursting head with an expansion cone, to which the pipe string is attached, is placed in the launch pit. A hydraulic pulling device is positioned in the reception pit. A pulling rod made up of numerous sections is inserted into the old pipe between the two pits. The hydraulic cylinder’s stroke corresponds exactly to the length of one section of the pulling rod. The bursting head is now attached to one end of the rod, and the other end is connected to the pulling device. As the rod is pulled, the bursting head breaks the cement pipe into pieces. The expansion cone behind it pushes the resulting fragments into the surrounding ground, making way for the larger-diameter replacement pipe that follows. In this way, the old pipe can be broken up, the channel widened and the new pipe pulled in in a single operation. After each pull, the crew in the reception pit removes the next section of the pulling rod from the pit. This process is repeated until the bursting head and the pipe behind it reach the reception pit. The pulling forces acting on the pipe are electronically recorded and documented throughout. Once installation is complete, the entire pipeline system is disinfected and pressure-tested.

Gerhard Dieringer is managing director of WDS Bau GmbH: “The welding machine supplied by AGRU worked perfectly. We divided the site into 12 sections for pipe bursting. We were able to burst and install 1 to 2 sections per day. We were very satisfied with AGRU Kunststofftechnik GmbH’s products and services, from preparation through to delivery and quality.”   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Warehouse & Logistiek

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.