THV Leieland completes works on the Leie in Harelbeke

THV Leieland completes works on the Leie in Harelbeke

The new year was marked by a festive official opening of the works on and around the lock and weir complex…

The new year was marked last weekend by a festive official opening of the works on and around the lock and weir complex in Harelbeke. The Temporary Joint Venture (THV) Leieland, formed by contractors Jan De Nul nv, Herbosch-Kiere nv, Engie Fabricom nv and Aelterman bvba, was responsible for the design and execution of the works.

Over the past five years, THV Leieland has worked on behalf of De Vlaamse Waterweg to renew and modernise the lock and weir, waterway and surrounding area along the Leie in Harelbeke.

Jan De Nul nv and Herbosch-Kiere nv were jointly responsible for the civil engineering works, as well as general coordination and reconciling the interests of all parties involved. Engie Fabricom nv carried out the electromechanical works, while Aelterman bvba was responsible for the steel construction. Their close collaboration resulted in an optimal design and high-quality execution, from a nautical, hydraulic, technical and aesthetic perspective.

Working in an urban area

The infrastructure works took place in the centre of Harelbeke. The Leie also had to remain open to shipping throughout the works. All of this had a direct impact on the construction methods and project planning.

THV Leieland opted to build a temporary lock so that shipping would not be disrupted by the works. A temporary weir prevented flooding during the works.

The new lock and weir were planned for the same location as the old ones to achieve an optimal nautical and hydraulic design. In other words, construction could only begin once the temporary infrastructure had been installed and the old infrastructure demolished.

Energy-neutral lock and weir complex

Alongside the new lock and weir complex, THV Leieland built a pumping station with two turbines. When there is excess water, the turbines will generate energy. Conversely, during dry periods and water shortages, the pumping station can pump water to the upstream water level. The expected energy output is higher than the consumption of the lock and weir complex, allowing it to be considered energy-neutral.

Seine Schelde project

The works on the Leie in Harelbeke are part of the wider Seine Schelde project, which is improving the waterway connection between the Seine basin and the Scheldt basin. Following several large-scale infrastructure projects in France, Wallonia and Flanders, inland vessels of up to 4,500 tonnes will be able to travel between Paris and Antwerp. These infrastructure projects include the renewal of locks, weirs and quay walls, deepening existing canals or digging new ones, and raising bridges.

Infrastructure works carried out by THV Leieland

  • Demolition of old infrastructure
  • New lock (230m long, 12,5 m wide x 4,70m water depth)
  • New weir (2 weir segments, each 12,5m wide)
  • Pumping station with turbines
  • Fish ladder
  • Quay walls (2 km)
  • Dredging works
  • Installation of the new steel Hogebrug (80m and 1,000 tonnes), Bloemmolenbrug (movable cycle bridge) and Banmolenbrug
  • Sewerage, district heating network and roads

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Warehouse & Logistiek

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.