The Factory of the Future takes shape in Venlo

Construction began in early March 2021 on a new, state-of-the-art production site for Hessing Supervers in Horst aan de Maas, Greenport Venlo. Alongside a Technical Services (TD) building, the project includes a state-of-the-art factory with around 65,000 m2 of floor space, housing more than 100 different production lines. With 46,000 m2 of ground-floor space and 17,500 m2 of upper-floor space, this is the largest project in the history of Bouwbedrijf van de Ven.
Hessing Supervers processes fresh fruit and vegetables into ready-to-cook products and prepared salads. Every week, the company supplies millions of packs of fresh, healthy products to fast-food chains, wholesalers, (inflight) caterers and supermarkets such as Jumbo, Sligro and PLUS, for which Bouwbedrijf van de Ven has already built large automated distribution centres. “For this project, we are responsible for the complete construction, installations and infrastructure works on behalf of Hessing Supervers,” says Mark Hamers, Project Manager at Bouwbedrijf van de Ven. “These installations include not only the mechanical and electrical systems, but also the sprinkler systems, refrigeration technology and some of the process installations (compressed air, chilled water, hot water, …). The installation for cleaning and disinfecting all process water is also noteworthy. The Factory of the Future uses and recovers huge amounts of process water. The entire building is also cooled, which places specific requirements on the materials and detailing.”

Distinctive central section
The Factory of the Future has a steel foundation, Hamers explains. “The central section is distinctive: it consists of a 15,000 m2 concrete first-floor slab on a steel foundation, with wide slab floors and beam bottoms. Concrete pits have also been installed, extending below the floor, which will house the process equipment for production. The rest of the structure is made of steel. The steel frame is now 30% complete. Once it reaches full height, the frame will be finished with roof panels featuring PIR insulation. Sandwich panels have been selected for the façade. The office section will be finished with curtain walls combined with a façade band of aluminium composite cladding.”
The TD building, which supplies all the installations, has a similar structure, with steel, façade panels and curtain walls. “Hollow-core slabs have been selected for the upper floors in this building.” The shell of the TD building is now complete, Hamers says. “We recently started the fit-out work here and are connecting all the technical systems.” In the future, the roof of the new building will be fitted with solar panels (5 MW). A 4,400 m3 water storage facility will also be built on site.

Food-safe and BREEAM-NL ‘Very Good’
On completion, the entire new building must meet stringent sustainability and food hygiene requirements. “The production site is being built to the BREEAM-NL ‘Very Good’ sustainability standard and will operate entirely on electricity. Waste heat from the refrigeration process will be used efficiently to heat spaces that require heating,” says Hamers. “A notable feature is the installation of around 45,000 m2 of walkable sandwich-panel ceilings, above which all the technical services will be concealed. A dedicated quality team will ensure that the building’s ‘low care’, ‘medium care’ and ‘high care’ zones are completed in strict accordance with their respective care requirements.”
The production areas in the Factory of the Future will be divided using sandwich panels. “The first areas are due to be handed over to ABB in May. ABB is responsible for the machinery and automation. The factory will be filled with machines for efficiently and quickly inspecting, washing, cutting, mixing and packaging thousands of kilos of fruit and vegetables,” says Hamers. Bouwbedrijf van de Ven is providing the services for these machines, including chilled and hot water, compressed air, technical gases, electricity and data. “Once the machines have been connected and tested, we will also install the final controls, fit impact protection and hang the doors.”
The new building is due to be handed over at the end of November. The first production machines will start up in early 2023. The new building is expected to be fully operational by the end of that year.
Question about this story? Ask your question
In this story
- ClientHessing Supervers
- ArchitectNieuweboer Architecten
- ContractorBouwbedrijf van de Ven (construction, installations and infrastructure work)
Keep following this
Get an email when a new story is published. No account needed.
- SubjectGeneral