Reserve pipeline for sewer at a water depth of 66 m

Reserve pipeline for sewer at a water depth of 66 m

Since the early 1970s, wastewater pressure pipelines have been installed in several lakes in Austria. This also applies to Fuschlsee in Salzburg, where a PE sewer pipeline has been in operation on the lakebed since 1975. As its calculated service life of 50 years is about to be reached, a parallel sewer pressure pipeline measuring 4,200 m in length needs to be installed. It will serve as a reserve pipeline that can be brought into operation immediately if problems arise with the old pipeline. AGRU Kunststofftechnik is supplying the components needed for the lake pressure pipeline, made from high-tech, stress-crack-resistant PE 100-RC plastic.

Lake pressure pipelines are quick to install and leave coastal areas, which are often protected natural areas, undisturbed during installation. They also require less pipework because the pipelines can be laid in straight lines. As a result, they cost less to install than a pipeline laid on land. However, because a pipeline laid in deep water is difficult to access if it is damaged, a replacement pipeline must always be available. For this reason, the Fuschlsee-Thalgau water treatment association is investing in a new parallel lake pressure pipeline made from PE 100-RC. The pipeline will run the full length of the crystal-clear mountain lake, whose water is so pure it is drinkable, and carry wastewater from the municipality of Fuschl am See. It will transport between 600 and 900 cubic metres of wastewater per day from one side of the lake to the other, where it will be routed via a collector to the wastewater treatment plant.

Ing. Erich Peer (second from left) and his son Manuel (far left) were responsible for the installation. Ir. Martin Roither (third from left) planned the lake pressure pipeline. Christian Winkler (right) is the managing director of the water treatment association.

AGRU Kunststofftechnik had previously supplied 4,248 linear metres of polyethylene pipe, with an OD of 280 mm and SDR 17 (16 mm wall thickness, maximum pressure of 10 bar), as well as fittings and a CNC-controlled butt-fusion welding machine. The black PE 100-RC pipes, with brown axial stripes for clear identification of their application (wastewater), offer exceptional resistance to point loading and stress cracking. The pipeline system therefore provides additional safety over decades of operation on the stony lakebed at a depth of 66 m, where the water temperature remains at just 4°C all year round due to the depth. The material also offers very good resistance to the chemicals found in domestic wastewater, such as alkalis and surfactants.

PEER WASSERBAU GmbH. & Co. KG. is a recognised specialist in hydraulic engineering, building construction and civil engineering, with extensive experience in the professional installation of lake pressure pipelines. To complete the pressure pipeline, which is more than 4 km long, engineer Erich Peer and his team must weld together 18-metre-long pipes and then lower them into the pipeline route, all within a short period of around two months. The AGRULINE pipes are welded using the AGRU ST CNC 2.0 butt-fusion welding machine. Its state-of-the-art control technology keeps all parameters, including pressure, temperature and time, under control at all times. The machine records the parameters for every individual weld, as well as the welder’s name. Only an experienced, certified welder may make the joints. Because the individual pipe sections are joined using only the pipe material itself, the result is a monolithic, continuously corrosion-resistant pipeline system.

The spacing between the weights was calculated so that exactly half of the empty pipe would be submerged.

Weight also plays an important role in lake pressure pipelines. Concrete weights must permanently prevent the pipeline system from floating, a problem that can be compounded by the possible formation of fermentation gases in the pipeline. The concrete weights also stabilise the pipeline on the lakebed, ensuring it remains in the same place decades later. PEER uses prefabricated concrete elements made up of two halves, which are placed around the plastic pipe like rings. The halves of each ring are then permanently joined with stainless steel bolts. A foam rubber insert is clamped between the pipe and concrete to protect the pipe and provide additional security against slippage. These concrete collars, fitted every 3 metres, compensate for around 50% of the buoyancy. Once the pipe is filled with water, the concrete weights will make it sink to the bottom.

AGRU Kunststofftechnik supplied the pipes, fittings and welding machines for the new lake pressure pipeline in Fuschlsee.

Around 200 linear metres of ready-to-use pipeline are pushed into the lake from the shore each day. The kilometre-long floating pipelines could drift in the wind, so PEER anchors them each day and keeps them taut. After around two months of work in all kinds of weather, it is time to lower the 4.2 km-long pressure pipeline to the lakebed. Several general conditions must be taken into account before this process can begin. It is important to map the lakebed in detail along the pipeline route, and to determine the exact position using GPS coordinates. The sinking process can then begin. To do this, lake water is carefully pumped into the pressure pipeline at one end, while compressed air is fed in at the other. The rate at which the pipeline sinks is critical, as it must not exceed a certain bend angle. After all, the future sewer will cross the entire length of the lake, including its deepest point at 66 m. The complete sinking process therefore takes several hours. Once the pipeline has been successfully sunk, the entire pressure pipeline is pressure-tested.

The Steinbacher + Steinbacher ZT GMBH office in Thalgau has many years of experience in municipal water engineering and has successfully completed several projects with the Fuschlsee-Thalgau water treatment association. For this reason, Ir. Martin Roither from the Steinbacher office was commissioned to plan the overall concept. This included a study of alternatives, planning, tendering and on-site construction supervision for the upstream retention basin, the pumping station and lake pipeline II through Fuschlsee.

Christian Winkler is managing director of Reinhalteverband Fuschlsee-Thalgau: “The water in Fuschlsee is of drinking-water quality, and it must stay that way. The new lake pressure pipeline serves as a reserve and gives us additional security, as it can be brought into operation within minutes in an emergency. In cooperation with Mr Martin Roither (planning and construction supervision), we therefore also opted for a plastic pipeline made from AGRU’s PE 100-RC, as studies have shown that a PE pipeline of this quality can last up to 80 years. We are satisfied with AGRU’s planning and delivery, as well as with the quality of its pipeline. I would also like to thank PEER for the professional and careful installation.”    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Warehouse & Logistiek

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.