Pontoons for service harbour in final design phase

Pontoons for service harbour in final design phase

The service harbour at the Nieuwe Sluis in Terneuzen will, of course, need to be fitted with the necessary pontoons. Van der Zalm Metaalindustrie BV has landed a major contract to design and build them. Simon Knaap tells us more.

“The harbour is in the outer harbour on the Westerschelde and has a usable length of 375 metres and a width of around 88 metres. It is completely rectangular, with an inlet in the embankment. We are responsible for all floating structures and bridges within the harbour,” Knaap begins. “That includes a service pontoon, mooring pontoons, access pontoons, several finger pontoons, a heavy-duty vehicle bridge and three footbridges. We will design, manufacture and install all of them.”

Floating pontoon

“The service pontoon is intended for loading and unloading goods and for use by emergency services. It is around 100 metres long and 12 metres wide, and consists of three sections. These will be floating pontoons moored to several piles. The pontoon will be accessed via the 43-metre-long, 4-metre-wide service bridge, which is hinged at one end to the retaining structure. Because of the large variations in water level, the other end rests on rollers on the service pontoon,” Knaap explains.

On the East mooring pontoon, he says: “This pontoon structure is 280 metres long and will be divided into 45-metre modules. It will rise and fall along piles and will be fitted with plastic fendering along the mooring line. It will be accessible via two footbridges, with the same hinged and roller arrangement as the service pontoon.”

Design challenges

Everything is still at the design stage, with account taken of the substantial forces that could arise in the service harbour. Knaap says: “There is a lot of wave action in the right-hand corner of the service harbour, more than elsewhere. For the pontoon, this means waves can deflect off it, collide with it and rebound. We are allowing for wave heights of 2.8 metres at 4-second intervals, which could occur once every 100 years according to Svasek studies. At those times, the whole structure is lifted into the air, creating a challenging engineering problem for us. That is why we are working closely with VNSC and external specialists on analyses and calculations. Detailed dynamic studies are needed to design a safe pontoon.”

Access pontoon and East mooring pontoon

An access pontoon is planned on the north-west side of the service harbour. “It consists of a floating tube with a platform, secured to tubular piles. The pontoon is intended to provide access to the wave screens and to allow small boats to moor.” The wave screens are designed to reduce incoming wave energy by around 80%.  

Like the service pontoon, the planned East mooring pontoon will be built to withstand heavy loads. This is necessary to accommodate larger boats and absorb impacts in emergencies. Knaap concludes: “We are busy with the design and have moved on from the preliminary design phase. The final design is now being developed and is expected to be completed in September. We also expect to have the detailed design ready this year.”

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Warehouse & Logistiek

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.