New glass-clad cycle parking facility at Station RAI triples capacity

On behalf of the municipality of Amsterdam, construction company J.P. van Eesteren has completely revamped the metro concourse and cycle parking facility at Station RAI. The cycle parking facility has been fitted with a stunning glass façade and roof. Capacity has increased from 500 to around 1,850 spaces.
The metro concourse has also been enlarged and refurbished in the style of the NS station, which was renovated five years earlier. The busy station, next to the RAI and Amsterdam Zuidas, remained open every day throughout the works. A key requirement from GVB and ProRail was that their passengers should not be inconvenienced. “And we managed that,” says J.P. van Eesteren project manager Sander Spoor. “The metro concourse was never closed for a single day, even though it is busy with pedestrians here from six in the morning until ten at night. That meant a great deal of night work, but also moving the barriers metre by metre during the day to keep the construction site as small as possible.”
Modelled in 3D in advance
The work involved demolition, earthworks, piling, and the installation of precast floors, a steel structure and glazing. It was extremely useful that the entire project had been modelled in 3D in a Building Information Model (BIM) before the renovation. Spoor: “That certainly helped us. A lot of glass was used in this project, and it has to fit. You can cut wood to size on site, but you can’t do that with glass.”
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectGeneral