Large-scale industrial site delivered in record time
Text Tim Janssens Beeld Frank Abbeloos

Delivering an industrial site of 5 hectares in just over a year, with around 25,000 m² of outdoor storage space, a 13,000 m² production hall and an adjoining office block, is an impressive achievement. Stadsbader pulled it off in the Port of Ghent, where it built a Flemish base for Walloon Brabant steel producer Armasteel. “Challenging projects like this are right up our street,” says project manager Ruben Raeymaekers.
Armasteel was founded in 1971. The company specialises in cutting, bending, prefabricating and installing reinforcing steel to order for all types of construction and infrastructure projects. To consolidate its strong market position, the company set its sights on a base in Flanders. It approached BVI.EU, which proposed a bespoke business complex with minimal environmental impact in the Port of Ghent. It was an ideal location, as Armasteel plans to transport most of its steel by sea. The search for a contractor capable of delivering both a large built-to-suit facility with production and office space and thousands of square metres of concrete external paving naturally led to Stadsbader.
Vertical integration as an advantage
“The first phase of our contract was to deliver the new building weather-tight,” says Ruben Raeymaekers, project manager at Stadsbader. “The large hall has a precast concrete beam-and-column frame, reinforced with horizontal and vertical steel bracing. The façade above the concrete plinths is clad in dark grey steel sandwich panels. From a construction point of view, the adjoining office block was somewhat more complex. Its load-bearing structure combines steel and concrete, with a steel truss supporting a large cantilevered upper floor. Installing this was no easy task, but thanks to the expertise of our skilled teams, the work went smoothly and efficiently. We lifted the elements into place with heavy-duty cranes and completed the assembly.”

“The enclosed ground-floor façades are clad in white concrete sandwich panels, a finish that is also used on the projecting canopies between the different storeys. Most of the remaining façade consists of curtain walls with extensive glazing. We were also responsible for the landscaping, and almost all the precast concrete elements were manufactured in-house at our Van Maercke Prefab production facility and installed by our own precast assembly teams.” Stadsbader’s strong focus on vertical integration once again proved a valuable advantage for the client.
Tight deadlines
The schedule set for this project was exceptionally tight. Armasteel wanted to bring its new hall into operation as soon as possible. “Planning is always critical in industrial construction, but in this case the schedule was extremely tight,” Ruben continues. “Production was due to start in March 2024, which meant the hall floor had to be poured in December 2023. The hall’s precast concrete frame was erected by two assembly teams, each working with a heavy-duty crane. This went very smoothly, and the frame was standing within just over a month. The roof and façades were then completed at speed. Finally, the hall floor was poured in six phases of around 2,000 square metres, at a rate of one phase per week. That, too, went extremely well, to Armasteel’s great satisfaction.”
“Although the weather was far from ideal, we still managed to meet the deadline,” Ruben concludes. “The site coming into operation in March had a considerable impact on the remaining work. From that point on, there were 5,000 tonnes of steel on site, so we had to work out a carefully planned sequence for laying the top layer of the concrete external paving. We are very pleased that everything went so smoothly. Challenging projects like this are right up our street, thanks to the speed and flexibility we can bring to bear across all our divisions.”