Construction of service harbour gets under way

After years of discussions with various maritime stakeholders, major work on the service harbour, a sub-project of Nieuwe Sluis Terneuzen, starts this week. In two years’ time (by the end of 2021), the service harbour and its building in Buitenhaven West can be brought into use. The harbour will be 385 metres long and 95 metres wide at its widest point.
The service harbour will be used by maritime service providers with a direct connection to the Terneuzen lock complex. A service building and access roads will also be constructed alongside the harbour. The new site is well placed in relation to the Nieuwe Sluis once it is complete.
Building
A building and berths for the Koninklijke Marechaussee, Boluda (formerly Kotug) and Muller Maritime Holding will be built at the service harbour. The vessels of these organisations will be moored in the harbour. Rijkswaterstaat has its Nautische Centrale Terneuzen at the same location.
Works
Preparatory work for the service harbour is in full swing. The construction site on Lange Middenhavendam has been set up, earth has been moved and the entrance has been modified to prevent construction traffic and traffic controllers travelling to the traffic control centre from crossing paths. This week, we will start vibrating in the new combi-wall. We will begin with one piling rig. A second piling rig will follow in early 2020. We are working from north to south. Piling work will be complete by mid-April 2020. In the second quarter of 2020, we will pump in approximately 100,000 m3 of sand to create a new section of land and a cofferdam.
Disruption
We will be carrying out vibration work from 9 December 2019 until mid-April 2020. The work is close to Terneuzen town centre and the communities of Wulpenbek and de Knol, and may cause noise and vibration nuisance. Construction traffic will also use the entrance on Buitenhaven more than usual.
We are carefully monitoring noise, vibrations and groundwater levels. More information is available on our website at www.nieuwesluisterneuzen.eu.
Nieuwe Sluis Terneuzen
The first vessel will pass through the Nieuwe Sluis in Terneuzen at the end of 2022. The Nieuwe Sluis will be the same size as the locks in the Panama Canal: 427 metres long, 55 metres wide and 16.44 metres deep. Construction is in full swing. In addition to work on the lock itself, a number of sub-projects are also under way, including work to make room for the entrance to the Nieuwe Sluis.