AWP 2.0: Always operational

AWP 2.0: Always operational

Waterschap Brabantse Delta will spend the coming years renovating and upgrading the existing wastewater pressure main (AWP). The pipeline runs from Moerdijk industrial estate to the Bath wastewater treatment plant. We spoke to project manager Adrie Giljam of GMB Waterkwaliteit & Installaties, the integrated main contractor, about the project and its challenges.

GMB is formally the main contractor, with the other parties acting as subcontractors. In practice, this distinction is barely noticeable and they are all partners.

A multidisciplinary approach and collaboration

As main contractor, GMB Waterkwaliteit & Installaties is carrying out the work together with its partners: Van der Kamp for the temporary pumping installations, Pentair Nijhuis for the pumps, Hoppenbrouwers for the electrical, instrumentation and process automation (E&PA), and RHDHV for the design. They are working under the name PAUW (Persstations AWP Ultieme Werking). “We were awarded the contract in July 2018 on the basis of EMVI,” says Giljam. “Traditional contract forms are increasingly giving way to agreements tailored to the client’s requirements. As the leading integrated water quality contractor in the Netherlands, we can make full use of our multidisciplinary approach and process engineering expertise. We have to, because the biggest challenge on this project is that the work must never bring wastewater transport to a standstill. The discharge capacity must be guaranteed. We combine ingenuity with predictability, certainty and safety. The latter is in our DNA.”

PAUW devotes considerable time and attention to building an effective working relationship with the client, as this is the foundation of a successful project. The team began with an extensive ProjectSamenwerkingsStartUp (PSSU) in June 2018, followed by quarterly ProjectFollowUp meetings (PFUs), where project objectives are regularly reviewed and discussed. At the end of August, the PAUW and Waterschap Brabantse Delta delivery teams held a PSSU-Uitvoering, focusing in depth on working together during the construction phase, with particular attention to safety. Various topics were discussed. As expected, the continuity of the AWP was a recurring theme. The team is also investing in collaboration within its own teams.  

GMB is formally the main contractor, with the other parties acting as subcontractors. “In practice, this distinction is barely noticeable and we are all partners,” says Giljam. “We are all working in the interests of the project, and therefore the client. Central direction is provided by GMB’s IPM team.” In addition to project management through the IPM organisation, GMB’s scope includes all building renovation, civil engineering modifications, infrastructure and pipeline work, and mechanical engineering activities. 

GMB is formally the main contractor, with the other parties acting as subcontractors.
In practice, this distinction is barely noticeable and they are all partners.

Work schedule

The pumping stations are being renovated in phases, for which GMB has scheduled the necessary shutdowns (UBNs). Giljam says: “We have already carried out one UBN for inspection work. A detailed work schedule is prepared for each UBN and agreed with Waterschap Brabantse Delta. It is crucial that these shutdowns are carried out safely and predictably, within the specified constraints.” 

At the Bath site, the emergency overflow was modified in June this year. Work is now in full swing at the Roosendaal pumping station. Building work has been carried out to accommodate the new transformers, and modifications have been made to the existing odour control system. The first new pump line in Roosendaal is due to be completed in March 2020. “Together with the water authority, we are on track to deliver a great project. The entire project will be completed in September 2022,” Giljam concludes. 

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Warehouse & Logistiek

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.