More than 11,000 m2 of aluminium window frames, doors and curtain walling systems

The Netherlands’ first multi-storey XXL logistics city hub features a high-quality aluminium facade. Commissioned by Bouwbedrijf Vrolijk, V.P.G. Aluminium Ramen en Geveltechniek B.V. supplied and installed more than 11,000 m2 of aluminium window frames, doors and curtain walling systems, including 10,000 m2 of curtain walling, 26 automatic sliding doors and 100 hinged doors. This makes Amsterdam Logistic Cityhub the largest project to date for the Nieuwkuijk-based facade specialist, which recently celebrated its 25th anniversary.
Amsterdam Logistic Cityhub
V.P.G. is extremely proud to have played a part in building this last-mile solution. It is also pleased to have once again earned the trust of Bouwbedrijf Vrolijk to supply and install the aluminium facade systems. “We have been working together for more than 20 years,” emphasises Richard van Zanten, director and owner of V.P.G. Aluminium Ramen en Geveltechniek B.V. “Following projects such as Fresh2You, Cornelisland I t/m V and Spoormaker, we were also involved in this project during the engineering phase. Together, we translated Convexarchitecten’s design into a practical, buildable execution design, without compromising the aesthetic quality envisioned by the architect and client.”
According to Van Zanten, choosing aluminium for this project was a logical decision given its waterside location. Aluminium also offers low weight, high strength and minimal maintenance. “The entire project was completed using curtain wall profiles and tall cover caps from system supplier Reynaers, extruded to project-specific lengths,” he says. “The CW 50 series was selected, while the windows and doors use CS 77. The entire project also features triple glazing.” V.P.G. began manufacturing the facade elements in early January 2022. Installation began just a few weeks later. All work was supervised by the facade specialist’s own site managers and project managers.
According to Van Zanten, the biggest challenge was the logistics. The curtain walls, with their very large areas of glazing, start at a height of 27 metres above ground level. Suspended access platforms were hung from the roof around the building, and installation was carried out from these. For glazing, V.P.G. used special cranes with considerable lifting height and reach. All products were delivered to the project just in time and installed immediately. The work was completed on schedule in August 2022.
Question about this story? Ask your question
Who worked on Amsterdam Logistic Cityhub
- precast concrete frameHolcon BVMentioned in One of the largest precast concrete projects currently under way
- architectConvex ArchitectenMentioned in One of the largest precast concrete projects currently under way
- aluminium kozijnen, deuren en vliesgevelsystemenV.P.G. Aluminium Ramen en Geveltechniek B.V.Mentioned in More than 11,000 m2 of aluminium frames, doors and curtain walling systems
- architectConvexarchitectenMentioned in More than 11,000 m2 of aluminium frames, doors and curtain walling systems
- curtain wall profiles and tall cover stripsReynaersMentioned in More than 11,000 m2 of aluminium frames, doors and curtain walling systems
- Property investor and managerCentral Trade Park (CTP)Mentioned in A new perspective on logistics property
Keep following this
Get an email when a new story is published. No account needed.
- ProjectAmsterdam Logistic Cityhub
- SubjectGeneral