A perfectly coordinated build [+video]

Text Elise Noyez Beeld Elise Noyez

A perfectly coordinated build [+video]

Group De Rudder has been active in the transport, storage and distribution of goods for more than 20 years. With four sites in West Flanders and Vilvoorde, 55,000 m2 of storage space and 92 lorries, the company has long outgrown its modest West Flemish roots, but its central base is still in Kuurne. It was there that the transport company first felt the need to expand, in 2016. Beeuwsaert Construct helped steer that growth.

Group De Rudder originally operated from a property it had purchased on Noordlaan in Kuurne. 

However, with 7,000 m2 of storage capacity and just two loading bays, the site had limited potential. In 2016, the company therefore decided to build a new distribution centre on a vacant plot in Pieter Verhaeghestraat, just around the corner. The facility needed not only a 4,500 m2 cross-dock, but also more than 10,000 m2 of storage capacity for both general goods and ADR goods. In its search for a reliable partner for this distinctive project, the company turned to Beeuwsaert Construct of Ledegem.

Full coordination

“This was our first construction project,” says CCO Xavier De Rudder. “It certainly wasn’t Beeuwsaert Construct’s. From the very outset, they guided us through the project in an extremely professional way. They presented an initial design tailored to our needs and the space available on the site, and put us in touch with all the specialist partners required for elements such as the racking, fire-suppression system and ADR bunker. With Beeuwsaert Construct taking care of the entire coordination, we could sleep soundly.”

Four sections

The distribution centre in Pieter Verhaeghestraat comprises four sections: a 4,500 m2 cross-dock with 20 loading bays, a conventional 9,000 m2 warehouse, an ADR bunker of around 1,500 m2 and a four-storey office building. All four sections can be accessed from a single central point in the building and are separated from one another by the necessary fire doors and gates. “The building was also quite literally constructed from these four sections, or corners,” says Xavier. “During construction, four teams were working here at the same time, gradually working towards one another. As a result, the construction phase went very smoothly. Everything was completed in just six months, including the car park and other external works.”

The dimensions of both the precast concrete panels and the sandwich panels were tailored to the size of the loading doors.

ADR bunker

The most challenging of the four sections was undoubtedly the ADR zone, where hazardous and highly flammable goods are stored. “The regulations are very strict,” says Xavier. “Fortunately, Beeuwsaert Construct knew exactly what was needed. The bunker is fitted with a foam fire-suppression system and sits in a watertight basin, recessed below the rest of the warehouse floor. In the event of an emergency, the room would therefore be filled with 4 metres of firefighting foam within one minute, without causing any pollution. The walls are also made of extra-thick concrete, so that even in the event of an explosion, everything would remain standing.”

Room to grow

The office building, like the ADR bunker, is built of concrete; elsewhere in the distribution centre, concrete was used only for the lower sections of the walls. Xavier says: “Forklifts are driven all over the building. It’s useful to use a robust material that can take a knock. Sandwich panels were used for most of the rest of the building. They allow us to work at a comfortable temperature here all year round, without heating.”

The dimensions of both the precast concrete panels and the sandwich panels were tailored to the size of the loading doors. Ten rooflights were also installed in the cross-dock. “As we’ve continued to grow, the cross-dock has increasingly become a storage area,” Xavier says with a laugh. “Since then, we’ve already built two more new buildings, including a new distribution centre in neighbouring Heule. We naturally turned to Beeuwsaert Construct again for that project. There are no specific construction projects on the agenda at the moment, but if we find a suitable site in the future, we will certainly contact Beeuwsaert Construct again.”  

Visit Beeuwsaert Construct at
Logistic & Industrial Build: Stand 1451

Have a business enquiry for Beeuwsaert Construct? Get in touch

Who worked on it

Group De Rudder distribution centre Kuurne in Kuurne

  1. volledige coördinatieBeeuwsaert Construct

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectGroup De Rudder distribution centre Kuurne
  • SubjectAutomation
  • CompanyBeeuwsaert Construct
Share this article

Advertisement

Follow Warehouse & Logistiek

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.