‘The future of distribution centres lies in repurposing brownfield sites’

Text Tim van Dorsten Beeld Corné Bastiaansen Photography en Van der Heijden

The distribution centre seen from above. (Image: Corné Bastiaansen Photography)
The distribution centre seen from above. (Image: Corné Bastiaansen Photography)

Prior knowledge speeds up construction of distribution centre

Is there an advantage to be gained by building a second phase of a distribution centre on a former landfill site? ‘Yes’, you might say, but given the challenges of the present day, that remains to be seen. Despite the challenges faced by construction company Van der Heijden, such as problems sourcing concrete and steel as a result of the war in Ukraine, Van der Heijden delivered on its promise and completed the project well ahead of schedule.

The distribution centre is located in Eindhoven-Noord, near Eindhoven Airport’. (Image: Corné Bastiaansen Photography)

The 28,000 m2 Prologis distribution centre in Eindhoven-Noord is the result of close collaboration between construction company Van der Heijden and its client, logistics property company Prologis. The prior knowledge gained by the construction company during the first phase of the project enabled it to complete the engineering work on time and start construction of the distribution centre. 

“We knew the war in Ukraine could cause supply problems,” says Jos van Tilburg, site manager at construction company Van der Heijden. “We told the client this even before signing the contract. Immediately after the agreement was signed in May 2022, we secured the supply of the key components to ensure they would be delivered on time. The team is now a well-oiled machine. We work well together and, cliché as it may sound, it’s all about making it happen together. On this project, everyone was willing to take responsibility when things got tough. The client and tenant(s), as well as the delivery partners, were all committed to making this a successful project. That meant we were able to pour the concrete foundations in July 2022.”

The distribution centre has two warehouses, each with 26 loading docks. (Image: Corné Bastiaansen Photography)

Focusing on opportunities and possibilities

However, sourcing the steel required for the distribution centre’s structure proved more difficult. “It arrived later than we had initially planned,” says Van Tilburg. “We discussed this challenge with the entire site team. At Van der Heijden, we approach things by looking for opportunities and possibilities. We have now got our partners thinking the same way. This approach requires commitment and flexibility from the whole team. We can only complete the construction work by coordinating closely with, and drawing on input from, all the parties involved. This fosters a sense of responsibility and helps us focus on what we can do.” 

Van der Heijden took a total of 9 weeks to build the steel structure. (Image: Corné Bastiaansen Photography)

Van der Heijden started building the steel structure shortly after the 2022 summer holidays and took a total of nine weeks to complete it. The construction team rose to the challenge, finishing the work well ahead of schedule. 

Site manager Jos van Tilburg. (Image: Van der Heijden)

Understanding requirements

Van der Heijden also had the advantage of knowing its client Prologis well, as this was the third project the Brabant-based construction company had completed for the logistics property company. 

Van Tilburg: “We are getting to know Prologis better and better. This enables us to understand its requirements and make proposals in advance. We work together to meet sustainability ambitions in relation to BREEAM and WELL Building certification. Through this redevelopment, Prologis is contributing not only to the region’s growth, but also to greater sustainability by making use of existing sites. And thanks to our prior knowledge of phase 1 of the project, which we completed in 2020, we saved time during the engineering phase,” says Van Tilburg.  

Question about this story? Ask your question

Who worked on it

Prologis distribution centre Eindhoven in Eindhoven

  1. construction companyVan der Heijden
  2. clientPrologis

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectPrologis distribution centre Eindhoven
  • ThemeLogistics property that grows with you
  • SubjectMaterial handling
  • CompanyVan der Heijden
  • CompanyPrologis
Share this article

Advertisement

Follow Warehouse & Logistiek

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.