Fast installation with an eye for detail

Distribution centres are getting bigger, more complex and more sustainable. At the same time, these buildings often have to be completed under pressure to meet their opening deadlines. Organising the construction process is no easy task. Daily cooperation with the coordinating contractor and other subcontractors is essential, say installers Ronald Duits (Kromwijk Elektrotechniek BV), Peter Moddejongen (vanPanhuis Hoogeveen) and Martien van de Beek (Unica Fire Safety). “You can only deliver a complex project like this under time pressure as a team.”
The three project managers are working together on the new main distribution centre and offices for clothing giant Scotch & Soda in Hoofddorp-Zuid. The site lies in a ‘pioneer area’ developed by Schiphol Area Development Company (SADC), between the A4 and the Schiphol line, where numerous large industrial buildings are planned. The warehouse for Scotch & Soda is being developed for Minerva Development and covers approximately 20,000 square metres. The new building has 16 loading docks, 1,200 m² of office space and a full basement with parking for 100 cars. The buildings are being constructed using traditional methods, with a steel frame, concrete plinth, steel roof decks and sandwich panels. This all-electric building is being completed at speed between October 2021 and May 2022, to WELL Building Standard certification. This is the first and only certification system specifically focused on the health and wellbeing of building occupants.

Intensive meetings
This spring, the project is entering a final sprint. To put it in context, the office section still needed to be enclosed by the end of March, while the warehouse is due for completion in April. “Our cooperation with main contractor DIJKHAM bouw is excellent,” says Duits, project manager for electrical installations. “Our client outsources virtually all the construction work to subcontractors, which means the façade, installation and finishing works are all progressing at the same time in the final phase. Everyone wants to get into the building at the last minute.” Project managers from the construction firms therefore have a shared meeting day once a week. “There’s no question that this is necessary,” says Moddejongen. “You can only deliver a project like this on time as a team. The human aspect matters too.
Over the past year, we have had to contend with rising material prices, longer lead times and a fair number of people being absent because of Covid. At the same time, the architect has their wishes and requirements, and the end user wants to occupy the building on time. You really have to work together to pick up the pace when needed.”

Fire protection systems
As project manager for mechanical services contractor vanPanhuis Hoogeveen, part of Top Installatiegroep, Moddejongen is involved in the project from start to finish, covering everything from drainage to building controls. Duits does the same for Kromwijk Elektrotechniek BV, the company responsible for most of the electrical installations, including an extensive lighting plan with daylight control and presence detection. Van de Beek is responsible for the sprinkler systems and related fire safety provisions in the building, including alarms for the sprinkler and fire detection systems, fire hose reels, fire brigade inlets and the sprinkler pump room and water supply. “The fire safety requirements are high because of the insurance conditions, so this work was assigned to a specialist full-service contractor such as Unica Fire Safety,” says Van de Beek. “Certification must of course be completed before the building is occupied, and sprinklers are a specialist field. It is one of our specialisms: we prefabricate all the pipework for our installations here, then deliver it ready to fit.”
Heaters and heat pumps
The DC for Scotch & Soda was designed to be all-electric. The warehouse is heated by heaters that blow warm air into the building and are controlled by air-to-water heat pumps. The roof will also be covered with solar panels. Moddejongen: “There is a huge amount of overlap between our work. That is certainly true of all-electric construction, where heat pumps are the primary energy source, because the electrical and mechanical services overlap. We also handle the building controls and remote monitoring, so cooperation is essential on every front.” For example, in BIM, with clash detection, adds Duits. The electrical services have the greatest exposure to logistical time pressure during handover, says the Kromwijk Elektrotechniek BV project manager. “Many installations can only be finished once the building is completely watertight and windproof. In the office section, which has a VRF system for climate control, that leaves an extremely short window. Most of the work is done by hand; only the busbar trunking is prefabricated.” Haarlemmermeer also faces a shortage of power supply capacity, an issue for the grid operators to resolve. Moddejongen: “All the construction projects in the area are affected. An ‘energy hub’ with a gas turbine for backup has therefore been set up to meet peak demand.”

Exposed pipework
As aircraft approaching Schiphol lower their landing gear just a few hundred metres overhead, Haarlemmermeer is growing at a rapid pace. Almost literally: in six months, a state-of-the-art distribution centre has taken shape here. “But it is still a people business, and the work is best carried out by permanent teams,” says Van de Beek. “This building is being delivered to the American WELL certification system, a bit like BREEAM, with a points system too, but with more focus on people and wellbeing,” says Moddejongen. Installers are also assessed in this area, and eventually even the sandwiches served in the office section. In the same part of the building, exposed pipework has to meet aesthetic requirements. “A lot of the pipework has deliberately been left exposed, but there must not be one bend too many,” says Moddejongen. “And every screw has to be exactly in the right place.” At the same time, the Scotch & Soda building has to meet stringent certification requirements so it can be occupied on time at the end of May. “That can only be achieved if the various subcontractors work together as a construction team under strong coordination,” the three conclude.
Question about this story? Ask your question
Who worked on Distributiecentrum Scotch & Soda Hoofddorp
- ClientMinerva Projectontwikkeling B.V.Mentioned in Healthy, stylish new-build for Scotch & Soda in Hoofddorp
- Building contractorDIJKHAM bouwMentioned in Healthy, stylish new-build for Scotch & Soda in Hoofddorp
- Electrical installationsKromwijk Elektrotechniek BVMentioned in Rapid installation with an eye for detail
- Mechanical services contractorvanPanhuis HoogeveenMentioned in Rapid installation with an eye for detail
Keep following this
Get an email when a new story is published. No account needed.
- ProjectScotch & Soda distribution centre Hoofddorp
- ThemeLogistics property that grows with you
- SubjectMaterial handling