Sustainable aluminium façade elements for new-build DC UTR06

DC UTR06 is taking shape on a brownfield site alongside the Amsterdam-Rhine Canal, at the Lage Weide industrial estate in Utrecht. The Intospace project comprises three warehouses and a four-storey car park on a single plot, with a combined area of approx. 59,752 m2. Sustainability is central to the design and construction of the distribution centre. The target is a BREEAM-NL ‘Excellent’ rating. The use of recycled end-of-life aluminium façade elements makes a significant contribution to this. The aluminium curtain walls and window frames for DC UTR06 are manufactured using SAPA aluminium profile systems. Like WICONA, SAPA is part of Hydro Building Systems. Kozijn Garant is responsible for manufacturing, supplying and installing the systems.

“For main contractor Wouters Schijndel, and based on Quadrant4’s aesthetic 3D/BIM design, we carried out the construction drawings for all the aluminium curtain walls, window frames, windows and doors, including the associated construction details,” says Rudy Heijligers, owner of Kozijn Garant. “Wouters Schijndel’s project engineers checked our drawings and provided feedback where necessary, after which we made a few further optimisations. Once the contractor had approved them, we went straight into production.”
Trusted partners
Wouters Schijndel is a trusted client for Kozijn Garant, says Heijligers. “We have previously supplied aluminium façade elements based on Hydro CIRCAL recycled aluminium for distribution centres for Zalando (Bleijswijk), H&M (Nieuwegein), fonQ (Utrecht), Kuehne + Nagel (Utrecht), Picnic (Utrecht) and Albert Heijn (Zaandam). The same goes for various distribution centres for Mainfreight in Zaltbommel and ’s Heerenberg, Kelders and Holland Food Service in Wijchen, and Tesla in Tilburg. The experience we have gained on these projects is proving invaluable here. The result is a smooth and well-organised construction process.”

Hydro CIRCAL is one of the world’s most sustainable aluminium alloys, says Marc van den Nieuwenhof, Area Manager at Hydro Building Systems Netherlands. “Hydro CIRCAL is high-quality aluminium containing at least 75% recycled end-of-life aluminium (post-consumer scrap), recovered from windows and façades in existing buildings. The higher the recycled content, the smaller the CO2 footprint. This project uses no less than 100% Hydro CIRCAL 75R!”
Lowest CO2 footprint
Smelting aluminium for new applications uses just 5% of the energy required to produce primary aluminium, Van den Nieuwenhof points out. “So the higher the proportion of recycled post-consumer scrap, the better for our cities and the environment. What’s more, aluminium can be recycled indefinitely without any loss of quality or material properties. We have now scaled up our production in the Benelux to the point where we use only Hydro CIRCAL for SAPA profile systems in the region. The production process is fully traceable, and the product is certified by an independent body (DNV-GL). Hydro CIRCAL has the lowest CO2 footprint in the world: around 2.3 kg of CO2 per kilo of aluminium. This is 86% lower than the global average for primary production (16.7 kg of CO2). This allows us to assure property developers, architects and investors that their projects meet all the requirements for sustainable building certifications such as BREEAM, LEED and DGNB, and helps us contribute to a better world.”
Minimal offcuts
All profiles for DC UTR06 are powder-coated to the specified colour (RAL 9011), cut to lengths of 6.5 and 7 metres and delivered in manageable crates to Kozijn Garant’s factory in Cuijk, says Heijligers.
“On arrival, all the profiles are thoroughly inspected. A sawing machine then cuts them to size, with a cutting list ensuring accurate dimensions. The profiles are cut as efficiently as possible, reducing offcuts and waste to a minimum.”
At the machining department, holes are drilled, slots and drainage channels are milled, and other preparatory work is carried out. “The profiles are then assembled using cleats, and the seals and hardware are fitted. Windows and doors are also hung here,” says Heijligers. “In warehouses B and C, automatic sliding doors will be installed alongside standard doors. We collect all the products and, in close consultation with the site managers and planners, transport them to the site just in time, where we carry out the installation.”
LARGE VOLUME, HIGH BUILDING SPEED
The main challenge on this project is the volume, combined with the high construction speed, he says. “In total, we will manufacture, supply and install 2,500 m2 of curtain walling, approximately 12 metres high and divided into 1-metre-wide sections, as well as 550 m2 of window frames. We are also supplying the cladding material for the car park and storm-resistant screen blinds for the offices. For the latter, we have engaged a sun-shading partner, who will handle delivery and installation based on our measurements.
Question about this story? Ask your question
Who worked on DC UTR06
- contractorWouters SchijndelMentioned in Sustainable aluminium façade elements for new-build DC UTR06
- production, supply and installationKozijn GarantMentioned in Sustainable aluminium façade elements for new-build DC UTR06
- aluminium profile systemsSAPAMentioned in Sustainable aluminium façade elements for new-build DC UTR06
- aluminium profile systemsHydro Building SystemsMentioned in Sustainable aluminium façade elements for new-build DC UTR06
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDC UTR06
- SubjectGeneral