Rapid installation with an eye for detail

(Visual CIIID – dd. dedato ontwerpers en architecten)
(Visual CIIID – dd. dedato ontwerpers en architecten)

Distribution centres are getting bigger, more complex and more sustainable. At the same time, these buildings often have to be completed under pressure to meet their opening deadlines. Organising the construction process is no easy task. Day-to-day cooperation with the coordinating contractor and other subcontractors is essential, say installers Ronald Duits (Kromwijk Elektrotechniek BV), Peter Moddejongen (vanPanhuis Hoogeveen) and Martien van de Beek (Unica Fire Safety). “Only as a team can you complete a project of this complexity under time pressure.”

The three project managers are working together on the new headquarters and distribution centre, or office, for clothing giant Scotch & Soda in Hoofddorp-Zuid. It is in a ‘pioneer area’ developed by Schiphol Area Development Company (SADC), between the A4 and the Schiphol railway line, where numerous large industrial units are planned. The warehouse for Scotch & Soda is being built for Minerva Development and covers approximately 20,000 square metres. The new building has 16 loading docks, a 1,200 m² office and a full basement with parking for 100 cars. The structures are being built using traditional methods, with a steel frame, concrete plinth, steel roof decks and sandwich panels. This all-electric building is being completed at breakneck speed between October 2021 and May 2022, in accordance with the WELL Building Standard sustainability certification. This is the first and only certification system specifically focused on the health and wellbeing of building occupants.

Power capacity is an issue in Hoofddorp. (Image: Fotografie Ringnalda)

Intensive meetings

This spring, the project is making a final push. For example, at the end of March the office section still needed to be closed in, while the warehouse is due for completion in April. “Cooperation with main contractor DIJKHAM bouw is excellent,” says Duits, project manager for electrical installations. “Our client subcontracts almost all the work, so the building envelope, installation and finishing work all have to progress in parallel in the final phase. Everyone wants to get into the building at the last minute.” The project managers from the construction companies therefore meet on the same day once a week. “There’s no getting around it, it’s essential,” says Moddejongen. “Only as a team can you deliver a project like this on time. The human element matters too.   

Over the past year, we have had to contend with rising material prices, longer lead times and quite a few absences due to coronavirus. At the same time, the architect has their wishes and requirements, and the end user wants to start using the building on time. You really have to work together to pick up the pace when needed.”

(Visual CIIID: dd. dedato ontwerpers en architecten)

Fire protection systems

As project manager for mechanical services contractor vanPanhuis Hoogeveen (part of Top Installatiegroep), Moddejongen is involved in every aspect of the project, from drainage to building management systems, from start to finish. Duits does the same for Kromwijk Elektrotechniek BV, which is responsible for most of the electrical installations, including an extensive lighting plan with daylight control and presence detection. Van de Beek is responsible for the sprinkler systems and related fire safety provisions in the building, such as alarms for the sprinkler and fire detection systems, fire hose reels, fire brigade inlets and the sprinkler pump room with its water supply. “The fire safety provisions are to a high standard because of the insurance requirements, which is why the work has been entrusted to a specialist such as Unica Fire Safety,” says Van de Beek. “Certification must of course be completed before the building can be occupied, and sprinklers are a specialism in their own right. It’s one of our areas of expertise: we prefabricate all the pipework for our systems here, then deliver it to site ready to fit.”

Heaters and heat pumps

The DC for Scotch & Soda has been designed as an all-electric building. The warehouse is heated by heaters that blow warm air into the building and are powered by air-to-water heat pumps. The roof will also be covered with solar panels. Moddejongen says: “There are a huge number of interfaces between our areas of work. That’s always the case with all-electric construction, where heat pumps are the primary energy source, because electrical and mechanical services overlap. We also handle the building management systems and remote monitoring, so cooperation is essential on every front.” This includes BIM and clash detection, adds Duits. According to the project manager at Kromwijk Elektrotechniek BV, the electrical installations face the greatest logistical time pressure during the handover phase. “Many installations can only be completed once the building is fully wind- and watertight. In the office section, which includes a VRF system for climate control, that leaves an extremely short window. Most of the work is done by hand; only the busbar trunking is prefabricated.” Haarlemmermeer also faces a shortage of capacity for electricity supply, an issue that lies with the grid operators. Moddejongen says: “All the construction projects in the area are dealing with this. An ‘energy hub’ with a gas turbine has therefore been set up to support peak demand.”

All the sprinkler pipes are prefabricated. (Image: Unica Fire Safety)

Exposed pipework

As aircraft approaching Schiphol lower their landing gear just a few hundred metres above, Haarlemmermeer is growing at a rapid pace. Almost literally: a state-of-the-art distribution centre is being built here in six months. “But it still takes people to do the work, and fixed teams are best placed to do it,” says Van de Beek. “This building is being delivered under the American WELL certification system, a bit like BREEAM, also based on a points system, but with a greater focus on people and wellbeing,” says Moddejongen. The installers are also assessed in this area, and ultimately even the sandwiches served in the office section. In the same part of the building, exposed pipework must meet aesthetic requirements. “A lot of pipework has deliberately been left visible, but there mustn’t be one bend too many,” says Moddejongen. “And every screw has to be exactly where it should be.” At the same time, the Scotch & Soda building must meet stringent certification requirements to be ready for occupation by the end of May. “That can only be achieved if the subcontractors work together as a construction team under strong coordination,” the three conclude.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeLogistics property that grows with you
  • SubjectGeneral
Share this article

Advertisement

Follow Warehouse & Logistiek

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.