Logistics warehouse with specific requirements

When several customers asked Nick De Winter, managing director at Belgium Warehousing & Logistics, to build a new logistics warehouse, he set his sights on a vacant plot along the Antwerpsesteenweg in Beerse. Within a few months, a high-performance building of around 5,000 m² had taken shape, including a semi-automated high-bay warehouse, a wide loading dock and a mezzanine with a load-bearing capacity of 100 tonnes. Given the plot’s limited accessibility, a string of special requirements and the after-effects of the coronavirus crisis, the project proved a real challenge for contractor ASK Romein, quite literally too …
Belgium Warehousing & Logistics is a logistics company that receives, stores and dispatches goods for customers in the chemicals and feed & food industries. The company’s new warehouse is around 100 metres wide, 50 metres long and 11 metres high. It comprises 4,919 m² of warehouse space and 86 m² of office space. “The loading dock at the front of the building can accommodate
three lorries for loading and unloading. The warehouse’s semi-automated high-bay section is reserved for pallet racking, which is positioned so close together that only a narrow-aisle truck or man-up truck can travel between the racks, guided by induction wires in the floor. The storage space is therefore optimised for fine-grained order picking or e-commerce,” says Nick De Winter. “Once the design was finalised, we joined forces with the architect to find a local contractor capable of bringing our ambitious plans to life. I had a very good feeling about ASK Romein from the outset. I also knew they had built KA Construct’s premises on the same business park and were constructing a similar logistics warehouse for a fellow company in Turnhout, so they had an excellent track record.”

Limited accessibility
Belgium Warehousing & Logistics’ new warehouse comprises a 190-tonne steel structure surrounded by a concrete plinth and sandwich panels. The façades of the adjoining office section are clad in silex concrete panels. The loading dock was built using poured concrete and retaining walls. “A mezzanine floor with a load-bearing capacity of more than 25 tonnes has also been installed above it, allowing certain goods to be tipped from above into silo trucks through a narrow slot. This can be done manually or using big bags and a steel beam with a hoist. While waiting for a particular vehicle, we can prepare an entire load, making the loading process quick and efficient,” explains Nick De Winter. One important detail is that lorries do not access the site directly from the Antwerpsesteenweg, but via the roundabout on the business park’s central access road. “Access to the public road is therefore very limited, which naturally posed a significant challenge during construction. The plot was also too low to accommodate the planned building programme in full, so we first had to raise it by a metre,” says Niels Vorselaars, project manager at ASK Romein.
Fire safety takes priority
During construction of the new warehouse, ASK Romein had to contend with a host of specific requirements. For example, it had to install an ultra-flat concrete floor in the high-bay section. “We had plenty of experience with this, but it is still more the exception than the rule,” says Niels Vorselaars. Fire safety presented another challenge, so Belgium Warehousing & Logistics brought in specialist consultancy FSEC. “Smoke curtains have been installed between the high-bay and low-bay sections of the warehouse, smoke vents with light-transmitting louvres have been integrated into the rooflights, and the office section is completely separated from the warehouse by a fire-resistant concrete structure … Given the nature of the goods stored in the building, we also installed a bund to contain firewater. As a result, the warehouse floor is 30 centimetres below datum, allowing us to create a watertight structure using the concrete plinth. That is why we also had to build access ramps at the side doors.”

Little space to work with
The utilities already on site were another crucial consideration. “A Fluxys gas pipeline runs between the new warehouse and the Antwerpsesteenweg. It is continuously monitored using pressure and movement sensors, so it cannot bear any load. Since we obviously could not position heavy equipment over it, we carried out most of the work from inside the building. High-voltage power lines also cross above the plot, affecting the warehouse’s volume and height. We had to use telescopic handlers to install all the building components safely. Finally,
a swale was planned right beside the warehouse, meaning we could not pave that area. In short, there was very little space to work with and we came closer to the plot boundary than expected on numerous occasions, so completing such a complex project in such a short time was no easy task,” says Niels Vorselaars. Nevertheless, construction of the warehouse took only a few months. It was handed over on 11 February 2022, much to the satisfaction of Belgium Warehousing & Logistics. “We had initially planned to finish before the Christmas break, but delivery problems caused by the coronavirus crisis put paid to that. Even so, we are very pleased with the result and with our excellent collaboration with ASK Romein,” concludes Nick De Winter.
Question about this story? Ask your question
Who worked on it
Logistieke opslaghal Belgium Warehousing & Logistics Beerse in Beerse
- ClientBelgium Warehousing & Logistics
- ArchitectArchitectenburo Louis Caron
- main contractorASK Romein
Keep following this
Get an email when a new story is published. No account needed.
- ProjectLogistieke opslaghal Belgium Warehousing & Logistics Beerse
- SubjectGeneral
- CompanyBelgium Warehousing & Logistics
- CompanyArchitectenburo Louis Caron
- CompanyASK Romein