JG Timmer built a new distribution centre with offices in Tiel for furniture importer Zijlstra Lefin B.V. The building has a total floor area of around 12,000 m2 and is connected to the existing building via an airlock. “We produced the drawings for the project’s distinctive architectural detailing ourselves.”

Construction began in August 2023, and the entire building was officially handed over in December 2024. The warehouse had already been in use for six months by then. JG Timmer project manager Pieter Kool: “At the time, this was the largest commercial building we had completed, and it is a great stepping stone to even larger projects. Construction went very smoothly. We had good communication with the client and our fellow members of the project team. We always try to be flexible, so we can still make changes during construction and ultimately deliver a building that meets every requirement. As with any construction project, there were some challenges, but no significant problems in this case.”

A mezzanine floor was installed above the loading docks, housing the showroom and offices.

Super-flat concrete floor

The building consists of a steel frame clad with sandwich panels. Given the building’s height of 17 metres and its use as a warehouse, a super-flat concrete floor was poured in situ. This prevents the forklift from swaying when operating at height. A mezzanine floor was installed above the loading docks, housing the showroom and offices. These spaces have hollow-core floors topped with anthracite-coloured concrete, which also serves as the floor finish. From the offices, employees can look straight into the distribution area. 

Industrial look with a luxurious feel

The stairwells and lifts feature exposed precast concrete, creating an industrial look with a luxurious feel. The exterior of the office section is made up of aluminium curtain walls with extensive glazing. Kool: “Large balconies extend from the rear of the office space, and it was quite a structural challenge to install them as cantilevers, particularly in combination with the curtain walls running all the way to the top. This distinctive architectural detailing is what makes it such a beautiful project. We produced the drawings for it ourselves.”

The entire building is heated with wood pellets. JG Timmer built a 17-metre-high concrete silo for this purpose, into which the pellets are blown to provide heating for both the offices and the warehouse. Kool looks back on the project with satisfaction. “We worked with companies we collaborate with regularly, and that is always a pleasant experience. The client also let us suggest contractors for the electrical and mechanical installations, cooling technology and sprinkler system.”     

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Advertisement

Follow Warehouse & Logistiek

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.