Construction of DC PLUS in Oss moves into the next phase

One of the most modern distribution centres in the Netherlands is taking shape on the Vorstengrafdonk industrial estate in Oss. Commissioned by PLUS, Bouwbedrijf van de Ven of Veghel is building a distribution centre covering over 46,000 m², with approx. 6,100 m² of office and communal space, 92 loading and unloading doors and a capacity of 400,000 packages a day. From mid-2022, the centre is due to supply all 270 PLUS supermarkets in the Netherlands, replacing the existing centres in Hendrik-Ido-Ambacht, Middenbeemster, Haaksbergen and Ittervoort.

Phase 1 of the project was completed on 29 July. Three days later, Witron began delivering and installing the warehouse racking and mechanical systems, including cranes, conveyors, lifts, robots and more. “This work will continue until mid-2022,” says Toon van Hout, Project Manager at Bouwbedrijf van de Ven. “In the meantime, the mechanical, electrical and sprinkler contractors need to install the final technical components in the automated area.” Bouwbedrijf van de Ven oversees the safety and health of workers on site, while the main contractor is also responsible for coordination and schedule monitoring. “We make sure all the relevant parties are on site in good time to install their components. Once a number of racking sections are complete, for example, the sprinkler contractor can install the in-rack sprinklers and sprinkler pipes. And once certain platforms have been built, the electrical contractor can install the lighting tracks. Air ducts and compressed air pipes also still need to be suspended in certain areas.” In the CPS area, Bouwbedrijf van de Ven is building the final structural pits, where Witron will later install its cranes and racking.
The structural and building services work must be completed in March/April 2022, allowing Witron to test and commission its systems. PLUS is expected to take the distribution centre into use in mid-2022. The new building will include dispatch areas for incoming and outgoing goods, a large packaging materials area and a workshop. Walkways are also planned in various locations. “We have also built an ADR cabinet for storing hazardous substances,” says Van Hout.
Concrete, steel and aluminium
The entire new building rests on foundations comprising concrete pads and ground beams. “On top of these, we built a steel structure with heights of 25, 18 and 14 metres respectively. The roof comprises steel roof sheets, stone wool insulation and a PVC membrane, while the façades are clad with steel liner trays and coloured steel outer sheets. The liner trays were insulated on site, after which the façades were finished with aluminium-framed windows, curtain walls and translucent polycarbonate panels. The office area features metal stud walls clad with HPL, glazed partition walls, suspended ceilings and carpet and PVC flooring.”

Infrastructure works
The loading docks are equipped with concrete loading bays. “We have also laid concrete, block paving and asphalt around the building, enabling Witron’s lorries to enter without bringing in dirt,” says Van Hout. “We also built an additional ramp. On the opposite side of the plot, we constructed a ground-level car park. An entrance building with a walkway to the offices has been built on the distribution centre site, so that employees and visitors do not cross paths with lorry traffic. The distribution centre grounds and the car park are also enclosed by railings, gates and barriers.”

BREEAM-NL ‘Outstanding’
He emphasises that the project was initially aiming for BREEAM-NL ‘Excellent’. “However, together with our BREEAM advisers, we identified opportunities to earn even more credits. This resulted in a BREEAM-NL ‘Outstanding’ design certificate. We are currently compiling the evidence for the corresponding post-construction certificate.”
The distribution centre’s sustainability measures include the use of materials, heat recovery and water management. “Once completed, the entire new building will operate entirely on electricity. Energy-efficient lighting will be used inside and out, and 11,000 PV panels are planned for the roof. We have also given considerable attention to thermal comfort and air quality, and integrated measures such as lighting controls, energy metering and leak detection. Construction waste has been actively sorted, and a predetermined proportion of recycled concrete aggregate has been incorporated into the concrete. Almost 12,000 infiltration crates underground are another notable feature, ensuring a steady drainage of water.”
Question about this story? Ask your question
Who worked on DC PLUS
- ClientPLUS Retail B.V.Mentioned in PLUS distribution centre in Oss enters next phase: ‘The building is complete, automation is in full swing’
- ArchitectDa Vinci Vastgoed BVMentioned in PLUS distribution centre in Oss enters next phase: ‘The building is complete, automation is in full swing’
- ConstructionBouwbedrijf L. v.d. Ven B.V.Mentioned in PLUS distribution centre in Oss enters next phase: ‘The building is complete, automation is in full swing’
- sprinklerABBS Nederland B.V.Mentioned in PLUS distribution centre in Oss enters next phase: ‘The building is complete, automation is in full swing’
- automated material handling systemWitronMentioned in PLUS distribution centre in Oss enters next phase: ‘The building is complete, automation is in full swing’
- Electrical contractorKanters Elektro B.V.In this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDC PLUS
- ThemeLogistics property that grows with you
- SubjectGeneral
- CompanyKanters Elektro B.V.