A quarter-kilometre distribution centre. Building from left to right
Text Liliane Verwoolde Image Hercuton

Most distribution centres are shaped like a solid rectangle. The distribution centre for AFL Barendrecht is also unusually long: 250 metres by 46 metres. This has implications for construction.

As an international transport company specialising in fruit and vegetables, AFL Barendrecht was looking for a new distribution centre. To make this happen, it approached Hercuton. Not only to deliver a building that met its needs, but also for support with financing. “Together, we reviewed all the options,” says Jack van den Broek, Commercial Manager at Hercuton. “We settled on a full lease of a new, purpose-built business premises.”

From left to right
The purpose-built premises for AFL comprise a chilled warehouse for storage and transhipment, covering 12,000 m2, a repacking department and office space for rental, a 4,000 m2 mezzanine floor, and an office for AFL itself. All of this is housed in a long, narrow building, with the office centrally located on the ground floor. “This had quite a few logistical implications,” says project manager Maikel Monde. “Normally, you build from the back to the front, and ideally you schedule construction of the office as early as possible. This is usually where most of the finishing work is required.”

A complex undertaking
After intensive planning, solutions began to emerge. With a left-to-right approach, the plant room, housing the equipment for the chill and freezer rooms and the main distribution board for the hall’s electrical system, is completed relatively quickly. The mezzanine floor is replaced with an enclosed upper floor, and large openings are made in two places in the floor for the goods and pallet lift. Monde: “That’s the gist of it, but it’s highly complex. Just think of the safety considerations involved when making openings in the upper floor while all kinds of work is also taking place below.” Extra attention is paid to the building’s Rc value and airtightness to keep the generated cold inside. To achieve this, the loading bays and levellers are positioned outside the front façade in freestanding dock shelters.

BREEAM ‘Excellent’
Given the high sustainability ambition, namely BREEAM ‘Excellent’ certification, Hercuton is opting for sustainable, circular materials and solutions. The building services will be ultra-energy-efficient, energy will be generated by solar panels, LED lighting will be fitted with motion sensors, and the concrete will be partly circular. “This is just a selection of the many environmental measures. Working to BREEAM certification standards is now a very familiar process for us.”

Safety comes first
The distribution centre is scheduled for handover, by agreement, on 1 August 2024. As things stand, that looks achievable. But Monde does add a caveat. “However carefully you plan, a period of rain, frost or storms can completely turn the schedule upside down. We then work with the subcontractors to see whether we can work more efficiently or differently to meet the schedule. Of course, only if safety can be assured.”
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ProjectAFL Barendrecht distribution centre
- ThemeLogistics property that grows with you
- SubjectGeneral